Building G with concrete apron and blacktop in.



Floor drains in all units.

In floor heat.

High quality construction features. Stone, siding, and Pella windows.

Sprinkler System

More high quality features. Copulas and gutters.

Almost done.

The Club House will go here in the coming months.
Construction Continues
Posted On: Aug 31, 2007

Road with curb and gutter in but no blacktop.

Building G

Finishing the concrete floor.

Lots of space.

Buildings from across the pond.
Building Construction Begins
Posted On: Jul 20, 2007

The first building is now going up.


Pond is finished and seeded.
Progress on June 1st, 2007
Posted On: Jun 02, 2007

Beginnings of the pond.

Digging out the pond. Note the retaining wall is completed and the flat area where the first buildings will go up.
Construction is Pedal to the Metal
Posted On: Apr 29, 2007


Dan Our Excavation Site Supervisor
Posted On: Apr 29, 2007


Road Coming Into The Complex
Posted On: Apr 29, 2007


Construction Begins
Posted On: Apr 02, 2007

The road coming into the complex


My how things have changed